The Shades Sunglass Company assembles sunglasses from frames, which it makes, and lenses, which it purchases from an outside supplier. The sales department has prepared the following 6-week forecast for Ebony, a popular model. The sunglasses are assembled in lots of 220, and the opening inventory is 300 pairs. Complete the projected available balance and the master production schedule.

Week Forecast Sales Projected Available Balance MPS 300 1 2 200 300 3 300 4 5 6 200 150 150