Question: A decision must be made between two very high-technology projects, Project $mathrm{X}$ and Project $mathrm{Y}$, both with a very short life of 3 years and

A decision must be made between two very high-technology projects, Project $\mathrm{X}$ and Project $\mathrm{Y}$, both with a very short life of 3 years and each having the same cost of $\$ 9,499$. The firm's normal MARR is $10 \%$. The difference is in the risk of each project, as shown below:

Project X Probability Net Cash Flow Project Y Probability Net Cash Flow

1. Identify which of the two projects is more risky.
2. If the riskier project has a MARR $2 \%$ higher than the company norm, what is the NPV for these projects?

Project X Probability Net Cash Flow Project Y Probability Net Cash Flow 0.25 $5,000 0.25 $0 0.50 9,000 0.50 8,000 0.25 12,000 0.25 20,000

Step by Step Solution

3.36 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 To identify which of the two projects is more risky we can compar... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Introduction Mechanical Engineering Questions!