An office wants to install an information system. The main tasks are below, with time estimates in

Question:

An office wants to install an information system. The main tasks are below, with time estimates in days and task dependencies indicated. Find the amount of time required to get the system up and running, and find the set of tasks which could delay the project if they were delayed.

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: