The Project Manager is trying to understand the relationship between different activities so he can create a diagram to understand how much time it will take. What is the PM doing?
A. Schedule Management Plan B. Define Activities, Sequence Activity C. Activity Duration Estimates, Schedule Baseline D. Control Schedule