Question: Based on lessons learned you realize that maintaining the integrity of project baselines has been a real challenge. It seems that some non-approved changes were
Based on lessons learned you realize that maintaining the integrity of project baselines has been a real challenge. It seems that some non-approved changes were released for incorporation into the project products and that some approved changes never made it into the project products. To better manage this in the future tighter control will need to occur in what process?
a. develop project management plan
b. direct and manage project work
c. monitor and control project work
d. perform integrated change control