Question: Work performance data is an input to control scope. This data comes from what process? a. develop project management plan b. monitor and control project

Work performance data is an input to control scope. This data comes from what process?

a. develop project management plan

b. monitor and control project work

c. perform integrated change control

d. direct and manage project work