Question: Change requests outputs from the Control Scope process are: Question 6 options: reviewed in the work performance data. reviewed in the Perform Integrated Change Control

Change requests outputs from the Control Scope process are:
Question 6 options:
reviewed in the work performance data.
reviewed in the Perform Integrated Change Control process.
sent directly to the Direct and Manage Project Work process.
reviewed in the Quality Assurance process.