Question: A manufacturing cell within a value stream has three processes and the following associated processing times: Drilling: 12 minutes Inserting: 6 minutes Finishing: 2 minutes

A manufacturing cell within a value stream has three processes and the following associated processing times:

Drilling: 12 minutes Inserting: 6 minutes Finishing: 2 minutes How many units can the cell produce per hour (on a continuous running basis)?

a. 10 units per hour

b. 3 units per hour

c. 5 units per hour

d. 30 units per hour Brief Exercise