Question: A manufacturing cell within a value stream has three processes and the following associated processing times: Drilling: 12 minutes Inserting: 6 minutes Finishing: 2 minutes
A manufacturing cell within a value stream has three processes and the following associated processing times:
Drilling: 12 minutes
Inserting: 6 minutes
Finishing: 2 minutes
How many units can the cell produce per hour (on a continuous running basis)?
1. 10 units per hour
2. 3 units per hour
3. 5 units per hour
4. 30 units per hour