Question: Given the project data below, which activities are critical and what is the length of the critical path? If activity E is reduced by 2
Given the project data below, which activities are critical and what is the length of the critical path? If activity E is reduced by 2 days, what additional activities become critical?
Activity A B C D E F G H I Duration 4 5 2 3 6 3 5 3 4 Precedents None None B A, B C, D C, D F E, F G, H
Step by Step Solution
★★★★★
3.26 Rating (161 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Below is the Network diagram Below are the paths ADFGI Length 19 days ADEHI Length 20 days ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
