Question: Given the project data below, which activities are critical and what is the length of the critical path? If activity E is reduced by 2

Given the project data below, which activities are critical and what is the length of the critical path? If activity E is reduced by 2 days, what additional activities become critical?Activity A B C D E F G H I Duration 4

Activity A B C D E F G H I Duration 4 5 2 3 6 3 5 3 4 Precedents None None B A, B C, D C, D F E, F G, H

Step by Step Solution

3.26 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Below is the Network diagram Below are the paths ADFGI Length 19 days ADEHI Length 20 days ... View full answer