Question: As a project begins to wind down, the project manager should: a. Release all nonessential personnel so that they can be assigned to other projects
As a project begins to wind down, the project manager should:
a. Release all nonessential personnel so that they can be assigned to other projects
b. Wait until the project is officially completed before releasing anyone
c. Wait until the line manager officially requests that the people be released
d. Talk to other project managers to see who wants your people