Question: As a project begins to wind down, the project manager should: A. Release all nonessential personnel so that they can be assigned to other projects.

As a project begins to wind down, the project manager should:
A. Release all nonessential personnel so that they can be assigned to other projects.
B. Wait until the project is officially completed before releasing anyone.
C. Wait until the line manager officially requests that the people be released.
D. Talk to other project managers to see who wants your people.

Step by Step Solution

3.40 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

A Release all no... View full answer