Question: Consider the following project information provided by a functional manager: Optimistic time for completion of the project is 12 weeks. Pessimistic time is 40 weeks.
Consider the following project information provided by a functional manager:
Optimistic time for completion of the project is 12 weeks. Pessimistic time is 40 weeks.
Most likely time is 25 weeks. Using the weighted average formula, what is the probability that the project will be completed between 14.33 weeks and 33.01 weeks?