Question: Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7 11 none
Use the following project information:
| Activity | Optimistic Time Estimate(weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) | ||||
| A | 2 | 7 | 11 | none | ||||
| B | 2 | 5 | 9 | A | ||||
| C | 4 | 6 | 12 | A | ||||
| D | 5 | 6 | 10 | B | ||||
| E | 6 | 10 | 17 | C | ||||
| F | 3 | 4 | 6 | D,E | ||||
| G | 3 | 6 | 10 | D,E | ||||
| H | 5 | 7 | 10 | F | ||||
| I | 5 | 8 | 11 | G | ||||
| J | 3 | 3 | 3 | H,I | ||||
(a) Calculate the expected completion time for this project.
(Round your answer to 2 decimal places, the tolerance is +/-0.01.)
Project completion time = weeks.
(b) Identify the activities included on the critical path of this project. (If there are several critical paths enter the first one from the alphabetical order.)
Critical activities:
ACEFHJ
ABDFHJ
ACEGIJ
ABDGIJ
.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
