Question: Problem 7 Use the following project information: Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 7

Problem 7

Use the following project information:

Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s)
A 2 7 11 none
B 2 4 8 A
C 5 8 12 A
D 5 7 11 B
E 4 9 17 C
F 3 4 5 D,E
G 2 5 8 D,E
H 5 6 12 F
I 4 7 12 G
J 3 3 3 H,I

(a) Calculate the expected completion time for this project.

(Round your answer to 2 decimal places, the tolerance is +/-0.01.)

Project completion time =

weeks.

(b) Identify the activities included on the critical path of this project. (If there are several critical paths enter the first one from the alphabetical order.)

Critical activities:

ABDGIJ

ABDFHJ

ACEGIJ

ACEFHJ

.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!