Question: Using the status chart in Figure 11-20 : (a) Estimate SV, CV, and TV, and compute SPI and CPI for week 30. Interpret the results.
Using the status chart in Figure 11-20 :
(a) Estimate SV, CV, and TV, and compute SPI and CPI for week 30.
Interpret the results.
(b) Compute ETC and EAC. Estimate the revised completion date and sketch the lines for forecast AC and forecast EV.