Question: Using the status chart in Figure13.21, answer the questions: a. Estimate SV, CV, and TV, and compute SPI and CPI for Week 30. Interpret the
Using the status chart in Figure13.21, answer the questions:

a. Estimate SV, CV, and TV, and compute SPI and CPI for Week 30. Interpret the results. b. Compute ETC and EAC. Estimate the revised completion date (ED), and sketch the lines for forecast AC and forecast EV