Question: What are the performance measurements for the Schedule Control process? A. SV (EV PV) and SPI (EV PV) B. SV (EV AC)
What are the performance measurements for the Schedule Control process?
A. SV (EV – PV) and SPI (EV ÷ PV)
B. SV (EV – AC) and SPI (EV ÷ AC)
C. SV (EV – BAC) and SPI (EV ÷ BAC)
D. SV (PV – EV) and SPI (PV ÷ EV)