Question: When a project or phase has been completed the project team should document results and formalize acceptance through the process of: a. Change control b.

When a project or phase has been completed the project team should document results and formalize acceptance through the process of:

a. Change control

b. Earned value analysis

c. Administrative closure

d. Performance reporting