Question: You are collaborating with Colleen, your project manager, on a project artifact that outlines how requirements will be analyzed, documented, and managed. What are the
You are collaborating with Colleen, your project manager, on a project artifact that outlines how requirements will be analyzed, documented, and managed. What are the required inputs to aid in creation of this document?
a. Scope management plan, requirements management plan, stakeholder register
b. Project charter, project management plan, scope management plan
c. Enterprise environmental factors, organizational process assets, charter, project management plan d.Enterprise environmental factors, organizational process assets, scope management plan, requirements management plan, stakeholder register