Question: Consider the dependency matrix and the activity durations provided above. a. Create a dependency matrix for the activities described, and build a project graph. b.

Consider the dependency matrix and the activity durations provided above.

a. Create a dependency matrix for the activities described, and build a project graph.

b. Find the critical path. What is the latest time the team can start working, assuming the venture fair is scheduled for April 18?

1 2 3 4 5 6 7 8 9 10 Activity Time

1 2 3 4 5 6 7 8 9 10 Activity Time 1 2 3 X X X X 1 5 2 4 X 3 00 4 5 6 X 3 4 8 5 X 5 1 X 6 12 7 8 9 10 X X 7 4 X 8 9 7 6 10 2

Step by Step Solution

3.48 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Sure I can help you with that a Dependency Matrix and Project Graph Based on the information in the image we can create the following dependency matrix Activity 1 2 3 4 5 6 7 8 9 10 1 X X X X X 2 X X ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management 6th Questions!