Question: Information-Providing Activity (Upstream) Q5.2. (10 Activities) Consider the dependency matrix and the activity durations provided above. a. Build a project graph, visually depicting the evolution
Information-Providing Activity (Upstream)

Q5.2. (10 Activities) Consider the dependency matrix and the activity durations provided above.
a. Build a project graph, visually depicting the evolution of this project.
b. Find the critical path. What is the earliest time that the project can be completed?
c. For each activity compute the late start, the late completion, and the slack time.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts