Question: Use Johnsons rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours. JOB
Use Johnson’s rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours.

JOB WORK CENTER 1 WORK CENTER 2 6 12 ABCDER 3 18 15 14 16 10 15 279485