Question: Use Johnsons rule to obtain the optimum sequence for processing the jobs shown through work centers A and B. JOB TIMES (hours) Job Work Center
Use Johnson’s rule to obtain the optimum sequence for processing the jobs shown through work centers A and B.

JOB TIMES (hours) Job Work Center A Work Center B a 2.50 4.20 b 3.80 1.50 C 2.20 3.00 d 5.80 4.00 e 4.50 2.00
Step by Step Solution
3.31 Rating (151 Votes )
There are 3 Steps involved in it
a Identify the smallest time job b 150 hours at work ... View full answer