Question: Use Johnsons rule to obtain the optimum sequence for processing the jobs shown through work centers A and B. JOB TIMES (hours) Job Work Center

Use Johnson’s rule to obtain the optimum sequence for processing the jobs shown through work centers A and B.

JOB TIMES (hours) Job Work Center A Work Center B a 2.50

JOB TIMES (hours) Job Work Center A Work Center B a 2.50 4.20 b 3.80 1.50 C 2.20 3.00 d 5.80 4.00 e 4.50 2.00

Step by Step Solution

3.31 Rating (151 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Identify the smallest time job b 150 hours at work ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management 6th Questions!