Question: SOLVED PROBLEM 1 5 . 4 Use Johnson's rule to find the optimum sequence for processing the jobs shown through two work centers. Times at

SOLVED PROBLEM 15.4
Use Johnson's rule to find the optimum sequence for processing the jobs shown through two work centers. Times at each center are in hours.
\table[[JOB,WORK CENTER 1,WORK CENTER 2],[A,6,12],[B,3,7],[C,18,9],[D,15,14],[E,16,8],[F,10,15]]