Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a working
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:
a. In order of most following tasks. Tiebreaker: greatest positional weight.
b. In order of greatest positional weight. Tiebreaker: most following tasks.
c. What is theefficiency?
.png)
Step by Step Solution
There are 3 Steps involved in it
Given Desired output rate 4 units per hourOperating time 56 minutes per hour We are given the tasks and their timesin minutes shown below a Use the most following tasks heuristic andin the case of a t... View full answer