Given the following processing times and due dates for six jobs, determine the optimum sequence using the

Question:

Given the following processing times and due dates for six jobs, determine the optimum sequence using the following rules: FCFS, SPT, EDD, and CR.

Due Date (in hours) Processing Time (in hours) Job 2.5 1.0 3.5 17 4.0 21 1.5 5.0 19