Question: Based on the data in Figure 14.13, complete a net material requirements schedule using lot-for-lot for: a) All items (7 schedules in all), assuming the
Based on the data in Figure 14.13, complete a net material requirements schedule using lot-for-lot for:
a) All items (7 schedules in all), assuming the requirement for A is 1.
b) All 7 items, assuming the requirement for all items is 1, except B, C, and F, which require 2 each.
Data from Figure 14.13
PERIOD Gross requirements: A ITEM A B D ON HAND LEAD TIME 122- 0 100 50 50 1 8 9 100 ITEM EFC G 10 50 ON HAND 75 75 75 11 12 150 LEAD TIME 2 2 1 B E A F G
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
a Net material requirements plan b Net material requirements plan ... View full answer