Question: Based on the data in Figure, complete a net material requirements schedule for: (a) All items (10 schedules in all), assuming the requirement for each
.png)
(a) All items (10 schedules in all), assuming the requirement for each BOM item is 1.
(b) All 10 items, assuming the requirement for all items is 1, except B, C, and F, which require 2each.
PERIOD 10 12 150 Gross requirements: A Gross requirements: H 100 50 100 50 LEAD TIME LTEM HAND TIME ITEM HAND 75 75 100 50 50 75 100 100 2
Step by Step Solution
3.46 Rating (169 Votes )
There are 3 Steps involved in it
a Net material requirements plan Week Item 1 2 3 4 5 6 7 8 9 10 11 12 A Gross requirement 100 50 150 On hand x 0 0 0 0 Net requirement 100 50 150 Orde... View full answer