Below you see the bill of materials and on the back of this sheet are the MRP plans for items

Question:

Below you see the bill of materials and on the back of this sheet are the MRP plans for items A, D, B, and C. Please answer the following questions:

1. Each unit of A requires how many units of B?

2. Each unit of A requires how many units of C?

3. What is the total lead time to produce item A? (including ordering all parts, making all subassemblies, and assembling A)

4. In period 4, the gross requirement for item C is 700 units.What action created that demand for 700 units of C?

5. What action(s), if any, should be taken right now? (“Right now” is period 1.)

B(1) 2 weeks 1 C(2) 1 week A 2 weeks C(1) 1 week D(2) 3 weeks B(1) 2 weeks C(2) 1 weekA Planned order releases D (L4L, LT=3) Gross requirements Scheduled Receipts Projected Available 0 0 Planned

6. If item C were ordered L4L instead of in lot sizes of 1500, what changes, if any, would you make in the planned order releases for C?

Period Planned order releases 1 2 3 5 7 8

7. The customer originally ordered 250 units of item A (lead time = 2 weeks) to be delivered in period 8. If the customer changes the order to 350 units of A, what changes, if any, should be made to the gross requirements for item C for the periods 1 through 8?

Period Gross requirements 2 3 4 5 6 7 8

8. The customer also wants the order delivered earlier. Howearly, if at all, can the order of 350 units be delivered?

This problem has been solved!


Do you need an answer to a question different from the above? Ask your question!

Step by Step Answer:

Related Book For  answer-question
Question Details
Chapter # 14- Resource Planning
Section: MRP EXERCISE
Problem: 1
View Solution
Create a free account to access the answer
Cannot find your solution?
Post a FREE question now and get an answer within minutes. * Average response time.
Question Posted: September 27, 2023 08:50:14