Question: Consider the following AON network and the data given in the following table to answer the next four questions. a. Identify the critical path. b.
Consider the following AON network and the data given in the following table to answer the next four questions.
a. Identify the critical path.
b. Find the earliest completion time of the project.
c. Find ES, EF, LS, and LF of each activity.
d. Find the slack for each activity.

A B E Activity A E G Time (Days) 5 6 19 7 4 BCDE 9 F 3 G 4