Question: For the CPM/PERT network in Problem 9.17, determine the probability that the network duration will exceed 50 months. Data in Problem 9.17 The following probabilistic

For the CPM/PERT network in Problem 9.17, determine the probability that the network duration will exceed 50 months.


Data in Problem 9.17

The following probabilistic activity time estimates are for the network in Problem 9.6:

Activity 1 2 3 4 5 6 7 8 9 10 11

Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest start and finish times
d. Activity slack
e. Critical path
f. Expected project duration and standard deviation

Activity 1 2 3 4 5 6 7 8 9 10 11 12 a 4 6 2 1 3 3 32 9 95 7 5 3 Time Estimates (Months) m 8 10 10 4 6 6 8 15 12 20 6 8 b 12 15 14 13 9 18 12 22 21 25 12 20

Step by Step Solution

3.46 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Expected activity times Activity Expected time 1 8 2 10 3 10 4 4 5 6 6 12 7 8 8 15 9 12 10 20 11 6 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!