The following probabilistic activity time estimates are for the CPM/PERT network in Problem Determine the following: a. Expected activity times
Question:
.png)
Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest starts and finishes times
d. Activity slack
e. Critical path
f. Expected project duration and standarddeviation