The following probabilistic activity time estimates are for the network in Problem.

The following probabilistic activity time estimates are for the network

Determine the following:
a. Expected activity times
b. Earliest start and finish times
c. Latest start and finish times
d. Activity slack
e. Critical path
f. Expected project duration and standarddeviation

b| 2 1 1 3 9 1 2 2 2 25 12 20 m-10 10-668 15 12 20 6 8 a462133295753 etw 123456789111

Step by Step Solution

3.52 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b c d Activity a m b t ES EF LS LF Slack 1 4 8 12 800 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

Excel file Icon

184_606c7cb6ebc56_143850.xlsx

300 KBs Excel File

Word file Icon

184-B-M-L-O-M (449).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!