Given the following data on planned and actual inputs and outputs of work center 4 of a

Question:

Given the following data on planned and actual inputs and outputs of work center 4 of a tool and die shop in terms of standard hours of work, determine the cumulative deviation and the backlog for each period. The beginning backlog is 15 standard hours of work:

2 3 Week 4 in 70 Planned input Actual input 60 55 65 60 55 70 65 70 45 Planned output Actual output 55 65 70 70 60 55 55

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: