Question: Given the following product structure tree, master production schedule, and routing and work standards information: 1. Develop a load projection report for each of the

Given the following product structure tree, master production schedule, and routing and work standards information:

J (2) L (2) K (1) N (2) M (4) 0 (3) P (1) Q (3) M (4)

Master Production Schedule Week 2 3 4 Product Z 100 100 120 160 130 70 Routing and Work Standards Number of Standard Hou


1. Develop a load projection report for each of the three work stations.

2. Balance the loads. Discuss the implications of shifting the work to other periods.

J (2) L (2) K (1) N (2) M (4) 0 (3) P (1) Q (3) M (4) Master Production Schedule Week 2 3 4 Product Z 100 100 120 160 130 70 Routing and Work Standards Number of Standard Hours of Operations Required Item Work Station Work per Unit Heat Treating 0.5 10 Machining 0.6 15 Machining 1.7 20 Heat Treating 1.0 25 Machining 1.5 30 N Heat Treating 0.5 35 Heat Treating 0.9 40 K Machining 0.8 45 Heat Treating 0.4 50 Assembly 1.0 CO

Step by Step Solution

3.48 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Master Production Schedule Week 1 2 3 4 5 6 Product Z 100 100 120 160 130 70 J2 200 200 240 320 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!