Question: Refer to problem 19. Using the information provided in that problem and the following data, prepare an MRP table for subassembly Q. The lot size

Refer to problem 19. Using the information provided in that problem and the following data, prepare an MRP table for subassembly Q.

Week 9 Gross Requirements 80 55 75 100 140 80 100 90 85


  • The lot size for Q is in multiples of 70.
  • There are 140 units of Q on hand at the beginning of week 1.
  • There is a scheduled receipt of 70 units of Q in week 2.

Week 9 Gross Requirements 80 55 75 100 140 80 100 90 85

Step by Step Solution

3.37 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Gross requirements indicated are for Q not finished product R Product Subassembly Q ... View full answer