Refer to problem 19. Using the information provided in that problem and the following data, prepare an

Question:

Refer to problem 19. Using the information provided in that problem and the following data, prepare an MRP table for subassembly Q.

Week 9 Gross Requirements 80 55 75 100 140 80 100 90 85


  • The lot size for Q is in multiples of 70.
  • There are 140 units of Q on hand at the beginning of week 1.
  • There is a scheduled receipt of 70 units of Q in week 2.