Question: Refer to problem 19. Using the information provided in that problem and the following data, prepare an MRP table for finished product R. The minimum

Refer to problem 19. Using the information provided in that problem and the following data, prepare an MRP table for finished product R.

4 6. 8. 9. Week Gross Requirements 20 25 35 85 70 95 55 70 80 85


The minimum production lot size for R is 60. Assume no beginning inventory.


Data from problem 19

A finished product R is assembled from two units of S and two units of Q. Production of S requires two units of K, three units of L, and one unit of M. Q is produced from two units of X and three units of Z.

4 6. 8. 9. Week Gross Requirements 20 25 35 85 70 95 55 70 80 85

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Product R Low level code 0 Lead time 2 weeks Lot size L4L DAY 1 2 3 4 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!