Table 7.8 contains data for the installation of imported generators from Germany in your office premises in Nigeria. The indirect

Question:

Table 7.8 contains data for the installation of imported generators from Germany in your office premises in Nigeria. The indirect costs are €200 per week, and a penalty cost of €900 per week will be incurred by your company for every week the project is delayed beyond week 50 days.
a. What is the shortest time duration for this project regardless of cost?
b. What is the total cost associated with completing the project using "normal" times?
c. What is the total time of the minimum-cost schedule?Activity A B C D E F G Immediate Predecessor(s) A B C D, E E Normal Time (days) 10 10 17 17 7 30 17 Crash

This problem has been solved!


Do you need an answer to a question different from the above? Ask your question!

Step by Step Answer:

Related Book For  answer-question

Operations Management Processes And Supply Chains

ISBN: 9781292409863

13th Global Edition

Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman

Question Details
Chapter # 7- PROJECT MANAGEMENT,,
Section: Problems
Problem: 15
View Solution
Create a free account to access the answer
Cannot find your solution?
Post a FREE question now and get an answer within minutes. * Average response time.
Question Posted: September 23, 2023 04:55:09