Question: Task E has an early start time of 3 days and an early finish time of 5 days, while it also has a late start
Task E has an early start time of 3 days and an early finish time of 5 days, while it also has a late start time of 10 days and a late finish time of 12 days from now. What is the slack in task E?
Step by Step Solution
3.34 Rating (154 Votes )
There are 3 Steps involved in it
Slack in a task represents the amount of time by whic... View full answer