Question: Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an

Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an early finish time of 5 days. What is the early start time of task C?

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The early start time of task C which has two immediate predecessors tas... View full answer