Question: Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an
Task C has two immediate predecessors, tasks A and B. Task A has an early finish time of 3 days, and task B has an early finish time of 5 days. What is the early start time of task C?