Question: Task E has an early start time of 2 days and an early finish time of 1 2 days, while it also has a late

Task E has an early start time of 2 days and an early finish time of 12 days, while it also has a late start time of 12 days and a late finish time of 22 days from now. What is the slack in Task E?