Question: The critical path is A-C-E-F and it is desired to complete the project in 10 days. Crash the necessary activities and determine the total costs,

The critical path is A-C-E-F and it is desired to complete the project in 10 days. Crash the necessary activities and determine the total costs, including the minimum crash costs.

Step by Step Solution

3.50 Rating (193 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The critical path time ACEF is 11 days so we wish to reduce the complet... View full answer