Question: Using the follow gin project information The critical path is A-C-E-G-I-J. (a) Calculate the probability that the project will be completed in 38 weeks. (b)
Using the follow gin project information
.png)
The critical path is A-C-E-G-I-J.
(a) Calculate the probability that the project will be completed in 38 weeks.
(b) Calculate the probability that the project will be completed in 42 weeks.
Immedlate Predecessor(s) ActlvtyOptlmlstic Time Pesslmlstlc Time Estlmates Varlance Estlmate(weeksLikely (weeks) Time Estlmates (weeks) (eks) 1000 0.444 1778 1000 3.361 6.00 5.00 7.33 7.67 10.17 4.00 5.83 6.33 8.00 3.00 4 12 10 16 4 10 4 D,E 0.694 0.694 1.000 0.000 D,E 10 H,I
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
Path Expected completion Time Variance 38 Week zvalue ... View full answer