Question: The table below shows estimates of activity times (weeks) for a project: Suppose that the critical path is A-C-E-F-G. What is the probability that the
The table below shows estimates of activity times (weeks) for a project:
.png)
.png)
Suppose that the critical path is A-C-E-F-G. What is the probability that the project will be completed.
a. Within 33 weeks?
b. Within30 weeks?
c. In more than 31 weeks?
Most Optimistic Probable Pessimistic Time Activity Time Time 2.5 3.5 5.5 10 12
Step by Step Solution
★★★★★
3.45 Rating (161 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Activity Mean Variance A 5 0111 B 3 0028 C 7 0111 ... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
1206-B-M-L-O-M(6317).docx
120 KBs Word File
