The table below shows estimates of activity times (weeks) for a project: Suppose that the critical path

Question:

The table below shows estimates of activity times (weeks) for a project:
The table below shows estimates of activity times (weeks) for

Suppose that the critical path is A-C-E-F-G. What is the probability that the project will be completed.
a. Within 33 weeks?
b. Within30 weeks?
c. In more than 31 weeks?