The following table provides the information necessary to construct a project network and project crash data. a.

Question:

The following table provides the information necessary to construct a project network and project crash data.


Activity Activity Time (weeks) Cost ($) Activity Activity Predecessor Normal Crash Normal Crash 20 1000 1480 24 20 1200


a. Construct the project network.
b. Determine the maximum possible crash time for the net-work, and crash the network the maximum amount possible.
c. Compute the normal project cost and the cost of the crashed project.