Question: The following table provides the information necessary to construct a project network and project crash data. a. Construct the project network. b. Determine the maximum

a. Construct the project network.
b. Determine the maximum possible crash time for the net-work, and crash the network the maximum amount possible.
c. Compute the normal project cost and the cost of the crashed project.
Activity Activity Time (weeks) Cost ($) Activity Activity Predecessor Normal Crash Normal Crash 20 1000 1480 24 20 1200 1400 3 14 700 1190 10 6. 500 820 3 11 550 730 4.
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
a b Present normal critical path 1 4 Normal critical path time 30 wk Crash critical path all cr... View full answer
Get step-by-step solutions from verified subject matter experts
