Question: The following table provides the crash data for the project network in Problem 9-13. The normal activity times are considered to be deterministic and not
.png)
Crash the network the maximum amount, indicate how much it would cost the bank, and identify the new criticalpath(s).
Activity Time (weeks) ActivityNormalCrash Activity Cost IS Normal Crash 7,000
Step by Step Solution
3.42 Rating (168 Votes )
There are 3 Steps involved in it
Project completion time 33 Normal cost 28800 Minimum project completion time 26 Crash cost 3390... View full answer