There are four activities on the critical path, and these activities have standard deviations of 1, 2,
Question:
There are four activities on the critical path, and these activities have standard deviations of 1, 2, 4, and 2 days, respectively. What is the standard deviation of this critical path?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (QA)
To calculate the standard deviation of the critical path w...View the full answer
Answered By
Ashington Waweru
I am a lecturer, research writer and also a qualified financial analyst and accountant. I am qualified and articulate in many disciplines including English, Accounting, Finance, Quantitative spreadsheet analysis, Economics, and Statistics. I am an expert with sixteen years of experience in online industry-related work. I have a master's in business administration and a bachelor’s degree in education, accounting, and economics options.
I am a writer and proofreading expert with sixteen years of experience in online writing, proofreading, and text editing. I have vast knowledge and experience in writing techniques and styles such as APA, ASA, MLA, Chicago, Turabian, IEEE, and many others.
I am also an online blogger and research writer with sixteen years of writing and proofreading articles and reports. I have written many scripts and articles for blogs, and I also specialize in search engine
I have sixteen years of experience in Excel data entry, Excel data analysis, R-studio quantitative analysis, SPSS quantitative analysis, research writing, and proofreading articles and reports. I will deliver the highest quality online and offline Excel, R, SPSS, and other spreadsheet solutions within your operational deadlines. I have also compiled many original Excel quantitative and text spreadsheets which solve client’s problems in my research writing career.
I have extensive enterprise resource planning accounting, financial modeling, financial reporting, and company analysis: customer relationship management, enterprise resource planning, financial accounting projects, and corporate finance.
I am articulate in psychology, engineering, nursing, counseling, project management, accounting, finance, quantitative spreadsheet analysis, statistical and economic analysis, among many other industry fields and academic disciplines. I work to solve problems and provide accurate and credible solutions and research reports in all industries in the global economy.
I have taught and conducted masters and Ph.D. thesis research for specialists in Quantitative finance, Financial Accounting, Actuarial science, Macroeconomics, Microeconomics, Risk Management, Managerial Economics, Engineering Economics, Financial economics, Taxation and many other disciplines including water engineering, psychology, e-commerce, mechanical engineering, leadership and many others.
I have developed many courses on online websites like Teachable and Thinkific. I also developed an accounting reporting automation software project for Utafiti sacco located at ILRI Uthiru Kenya when I was working there in year 2001.
I am a mature, self-motivated worker who delivers high-quality, on-time reports which solve client’s problems accurately.
I have written many academic and professional industry research papers and tutored many clients from college to university undergraduate, master's and Ph.D. students, and corporate professionals. I anticipate your hiring me.
I know I will deliver the highest quality work you will find anywhere to award me your project work. Please note that I am looking for a long-term work relationship with you. I look forward to you delivering the best service to you.
3.00+
2+ Reviews
10+ Question Solved
Related Book For
Question Posted:
Students also viewed these Business questions
-
Suppose the R2 for a bivariate regression is equal to 1. This tells us that: O a. The slope coefficient is equal to 1 or -1. O b. The correlation between the dependent and independent variables is...
-
Prepare the report that Vicky Roberts requested, assuming the project will begin immediately. Assume 45 working days are available to complete the project, including transporting the car to Detroit...
-
Report Format Market analysis Business - Pizza Vending Machine - Target Place : Universities 1. Target Market University Students in the UK University food 2. Potiential Customers 3. Barrier of entry...
-
On January 1, 2012, Picante Corporation acquired 100 percent of the outstanding voting stock of Salsa Corporation for $1,765,000 cash. On the acquisition date, Salsa had the following balance sheet:...
-
Simonies Company, which uses iGAAP, has a note receivable with a carrying value of $30,000 at December 31, 2010. On January 2, 2011, the borrower declares bankruptcy, and Simonis estimates that only...
-
Because of the velocity deficit, \(U-u\), in the boundary layer, the streamlines for flow past a flat plate are not exactly parallel to the plate. This deviation can be determined by use of the...
-
The following control procedures are used at Aldean Company for over-the-counter cash receipts. 1. To minimize the risk of robbery, cash in excess of $100 is stored in an unlocked attach case in the...
-
Khairul bought a television set with cash price of Rm6000. He paid a 10% down payment and the balance was settled by making a 24 monthly payments . If the interest was 8% per annum on the original...
-
A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days. The second path has an expected length of 11 days and a variance of 1...
-
A project network has a total of four paths running through it. These four paths vary in length, from a minimum of 4 days long to a maximum of 18 days long. How long will this project take to...
-
In Problems, evaluate each logarithm without using a calculator. In Problems 1317, check with the change-of-base formula. e ln 5
-
11.) Bella purchase a new pair of shorts from Athleta. The shorts were on sale for $14.99 and were originally priced $49.99. What was the percent of discount the shorts were marked down? Round your...
-
Rewrite the class declaration to follow best practices, e.g., operators, three important functions, and printing. The functions you write must be const-correct. You do not need to create, an...
-
A JK flip flop is used to realize a Toggle (T) flip flop by tying both inputs together to a single value as shown. When T = 1, the output will toggle, and when T = 0, it will hold. At time t = 0, T =...
-
Light travels at roughly 3.00108ms. What is this speed in miles per minute? Use 1mi=1609.344m and 60s=1min. Report your answer in scientific notation with three significant figures. Use the...
-
(20 pts.) Topological Sort. Run the DFS-based topological ordering algorithm on the following graph. Whenever you have a choice of vertices to explore, always pick the one that is alphabetically...
-
How many times does a typical person blink her eyes in a lifetime?
-
What key concerns must functional tactics address in marketing? Finance? POM? Personnel?
-
Cameron Lopez was having a roller-coaster type of day and was trying to make sense of it all as she sipped her Starbucks Mocha-Frappuccino in the departure lounge in San Francisco Airport. Cameron is...
-
One year ago, your company purchased a machine used in manufacturing for $100,000. You have learned that a new machine is available that offers many advantages and you can purchase it for $155,000...
-
Find the inventory value using the weighted average method, the FIFO method, and the LIFO method. Purchases Beginning inventory: 25 units at $8 Find the inventory value using the weighted average...
Study smarter with the SolutionInn App