Question: A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days.
A project network has two paths running through it. The first path has an expected length of 10 days and a variance of 2 days. The second path has an expected length of 11 days and a variance of 1 day. What is the probability that this project can be completed in 12 days?