Question: This Active Model appears in myomlab. It allows you to evaluate the sensitivity of che project time to changes in activity tunes and activity predecessors.

This Active Model appears in myomlab. It allows you to evaluate the sensitivity of che project time to changes in activity tunes and activity predecessors.

QUESTIONS
1. Activity B and activity K are critical activities. Describe the difference that occurs on the graph when you increase activity B versus when you increase activity K.
2. ActIvity F is not critical, Use the scroll bar to determine how many weeks you can increase activity F until it becomes critical.
3. Activity A is not critical. How many weeks can you increase activity A until it becomes critical? What happens when activity A becomes critical?
4. What happens when you increase activity A by one week after it becomes critical?
5. Suppose that building codes may change and, as a result, activity C would have lo be completed before activity D could be started. How would this affect the project?

Step by Step Solution

3.50 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

When activity B is increased the project time will also increase because activity B is a critical ac... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!